Cluster · estimate · FY 2025
Estimated cost for patching as part of the 2025 overlay project.
Not promoted to the official baseline.
This cluster is useful evidence for review. It does not drive the budget simulator until an admin confirms the amount against an official source and promotes it.
Corroboration
1docs
Consensus
0%
Votes attached
0
Date range
2025-02-27 — 2025-02-27
Estimated cost for patching as part of the 2025 overlay project.
Engineer Nelson went over the 2025 feasibility report for the 2025 overlay project. He explained details regarding the project including which roads need patching, how the overlay will be 1.5 inches thick, and how he is not aware of any drainage issues. He also mentioned that the cost for patching is estimated at $37,400 and the estimate for the overlay is $366,080 with a total for the project being $403,480.