Liquidated damages rate for late final completion in 2019 Road Improvement Projects contract.
Not promoted to the official baseline.
This cluster is useful evidence for review. It does not drive the budget simulator until an admin confirms the amount against an official source and promotes it.
Corroboration
1docs
Consensus
0%
Votes attached
0
Date range
2019-04-09 — 2019-04-09
Liquidated damages rate for late final completion in 2019 Road Improvement Projects contract.
Liquidated damages of $300 per calendar day is proposed for each day that expires after the time specified for achieving final completion.
Reasoning: This is a contractually specified penalty amount.