Every dollar in any document
Loading records…
Loading records…
Cluster · estimate · FY 2019
Estimated construction cost for Jasper Street Improvement project (Schedule A).
Not promoted to the official baseline.
This cluster is useful evidence for review. It does not drive the budget simulator until an admin confirms the amount against an official source and promotes it.
Corroboration
2docs
Consensus
33%
Votes attached
0
Date range
2019-06-11 — 2020-01-14
Estimated construction cost for Jasper Street Improvement project (Schedule A).
Figure 4 - Residential Improvement - Preliminary Cost Estimate ESTIMATED CONSTRUCTION COST SCHEDULE "A" $ 346,660.00
Reasoning: Subtotal for construction cost in cost estimate table.
Estimated construction cost for Jasper Street Improvement Project (Schedule A).
Figure 4 - Residential Improvement - Preliminary Cost Estimate ESTIMATED CONSTRUCTION COST SCHEDULE "A" $ 346,660.00 ENGINEERING, LEGAL, AND ADMINISTRATIVE $ 34,000.00 FINANCING COSTS $ 10,300.00 TOTAL ESTIMATED PROJECT COST $ 390,960.00
Reasoning: Line item in the cost estimate table for construction costs.