Cluster · estimate · FY 2019
Estimated engineering, legal, and administrative costs for Jasper Street Improvement Project.
Not promoted to the official baseline.
This cluster is useful evidence for review. It does not drive the budget simulator until an admin confirms the amount against an official source and promotes it.
Corroboration
1docs
Consensus
0%
Votes attached
0
Date range
2019-06-11 — 2019-06-11
Estimated engineering, legal, and administrative costs for Jasper Street Improvement Project.
Figure 4 - Residential Improvement - Preliminary Cost Estimate ESTIMATED CONSTRUCTION COST SCHEDULE "A" $ 346,660.00 ENGINEERING, LEGAL, AND ADMINISTRATIVE $ 34,000.00 FINANCING COSTS $ 10,300.00 TOTAL ESTIMATED PROJECT COST $ 390,960.00
Reasoning: Line item in the cost estimate table for engineering/legal/admin.